Civil society in court to challenge gas power plant in Richards Bay

The case will be heard in the Pretoria High Court on 2 and 3 August 2022. Picture: jessica45/Pixabay

The case will be heard in the Pretoria High Court on 2 and 3 August 2022. Picture: jessica45/Pixabay

Published Aug 1, 2022

Share

The South Durban Community Environmental Alliance (SDCEA) and local social and environmental justice organisation, groundWork, will be taking to the Pretoria High Court next week to ask that it set aside the environmental authorisation granted to Eskom for the construction of a combined cycle power plant in Richards Bay.

This landmark litigation marks the first time that a gas-to-power plant has been challenged in a court in South Africa. SDCEA and groundWork are supported by Natural Justice and Green Connection and represented by law firm Cullinan & Associates.

In a press release, Natural Justice said Eskom was granted environmental authorisation in December 2019, although construction on the project has not yet begun. The gas-to-power plant will be fuelled by gas via a pipeline that will be installed from the Richards Bay Port and will supply up to 3000MW of energy.

In their court papers, SDCEA and groundWork have called for the environmental authorisation to be declared unlawful and set aside based on inadequacies within the environmental impact assessment (EIA) and due to the public participation process that was undertaken being flawed.

In the Earthlife Africa judgment handed down in 2017, the Constitutional Court said climate change impacts must be assessed before issuing an environmental authorisation for a proposed project.

In the current case, SDCEA and groundWork argue that there was an inadequate assessment of the climate change impacts of the project, with evidence showing that a gas power plant, such as the one proposed, emits as many greenhouse gases as other fossil fuels, like coal, during the entire life-cycle of a project.

Natural Justice argued that the EIA failed to provide a sufficient analysis of the need and desirability of the gas-to-power plant. In fact, the applicants filed an expert report which found that combined cycle capacity is not needed in the next decade, and that 3000MW of combined cycle capacity would not be needed until 2041 at the earliest.

Other studies have confirmed this. Developing this project will lock South Africa into long-term fuel cost commitments, and this is neither needed nor desirable. The court papers also argue that the decision makers should have considered that renewable energy is an alternative fuel source.

The gas-to-power plant will be linked via a pipeline from the Richards Bay Port. The impact of this was not considered in the EIA, and hence it failed to consider the cumulative impacts of the pipeline, as well as the many other gas projects proposed in Richards Bay.

They argue that the public participation process for this development was also flawed, as many communities were excluded from the public participation process. These included traditional communities in surrounding rural areas. The information about the project was also advertised exclusively in English despite the EIA report itself recognising that 79% of the population of uMhlathuze Municipality, where Richards Bay is situated, speaks isiZulu.

Desmond D’Sa of the SDCEA said that “climate change is a present issue that many communities are facing, and the most vulnerable suffer. The April floods that took place in KwaZulu-Natal is clear evidence of this.

“A gas-to-power plant in Richards Bay will exacerbate climate change and lock South Africa into fossil fuel development that undermines what was signed in Glasgow and in terms of the Paris Accord, which is the need to move away from fossil fuels and dirty fuels,” he said.

“Eskom's actions will impact severely on the present and future generations.”

The case will be heard in the Pretoria High Court on 2 and 3 August 2022.

Current Affairs